Progress Report on Youth Development Schemes

 

Musarrat Ullah Jan – Kikxnow digital creator

Upgradation of Battakundi Youth Hostel (Phase-I) has been finished with 100% financial and physical progress, using the entire cost of 33.00 million.

Construction of Peshawar Youth Complex has registered 64% financial progress (307.231 million incurred out of 474.499 million) and 72% physical completion, with good quality work in progress.

The Jawan Markaz Mohmand stands at 100% financial absorption (111.00 million expended) and 98% physical achievement. Only finishing touches are left.

The Jawan Markaz Swabi reflects 32% financial achievement (34.76 million expended out of 107.350 million) and 50% physical accomplishment. Physical progress is lagging behind financial disbursement, reflecting potential delay in fund release.

The Jawan Markaz Mardan has expended 32% of money (46.02 million out of 146.060 million) but has made 80% physical progress, indicating effective implementation despite reduced expenditure.

The Jawan Markaz D.I. Khan has made 37% financial progress (40.67 million spent out of 111.380 million) and 60% physical completion, indicating consistent progress but needing close supervision.

The Jawan Markaz Haripur falls behind with just 29% financial advancement (42.47 million out of 148.430 million) and 40% physical completion, requiring pick-up pace to achieve goals.

The Jawan Markaz South Waziristan Lower is the slowest, with 22% financial advancement (37.62 million out of 171.062 million) and 35% physical completion. Urgent intervention is required to accelerate work.

#YouthDevelopment #KPK #Pakistan #JawanMarkaz #YouthEmpowerment #InfrastructureDevelopment #SportsAndYouth #DevelopmentUpdate #PakistanYouth #ProgressReport

Comments

Popular posts from this blog

Govt urge open wedding halls in KP, owners

Mohmand Bajaur Aman Cycle Race Promotes Peace and Local Talent

Demand for an inquiry into the contracts and contracts awarded in the previous regime