Progress Report on Youth Development Schemes

 

Musarrat Ullah Jan – Kikxnow digital creator

Upgradation of Battakundi Youth Hostel (Phase-I) has been finished with 100% financial and physical progress, using the entire cost of 33.00 million.

Construction of Peshawar Youth Complex has registered 64% financial progress (307.231 million incurred out of 474.499 million) and 72% physical completion, with good quality work in progress.

The Jawan Markaz Mohmand stands at 100% financial absorption (111.00 million expended) and 98% physical achievement. Only finishing touches are left.

The Jawan Markaz Swabi reflects 32% financial achievement (34.76 million expended out of 107.350 million) and 50% physical accomplishment. Physical progress is lagging behind financial disbursement, reflecting potential delay in fund release.

The Jawan Markaz Mardan has expended 32% of money (46.02 million out of 146.060 million) but has made 80% physical progress, indicating effective implementation despite reduced expenditure.

The Jawan Markaz D.I. Khan has made 37% financial progress (40.67 million spent out of 111.380 million) and 60% physical completion, indicating consistent progress but needing close supervision.

The Jawan Markaz Haripur falls behind with just 29% financial advancement (42.47 million out of 148.430 million) and 40% physical completion, requiring pick-up pace to achieve goals.

The Jawan Markaz South Waziristan Lower is the slowest, with 22% financial advancement (37.62 million out of 171.062 million) and 35% physical completion. Urgent intervention is required to accelerate work.

#YouthDevelopment #KPK #Pakistan #JawanMarkaz #YouthEmpowerment #InfrastructureDevelopment #SportsAndYouth #DevelopmentUpdate #PakistanYouth #ProgressReport

Comments

Popular posts from this blog

Mohmand Bajaur Aman Cycle Race Promotes Peace and Local Talent

Is Khyber Pakhtunkhwa Sports Directorate for Sports Development or Profit?

Badminton and Ramadan: Finding Balance During the Holy Month