Peshawar's "Piyo System": A Father of All Delays for the Tartan Track
Musarrat Ullah Jan . Kikxnow , digital creator
The Peshawar Sports Complex football and athletics ground
has remained stuck in a project that is neither finished nor properly shelved
for years now. The objective was to lay an international-standard tartan track,
but five years on, athletes still lack a field, no events have been organized,
and nobody has been held accountable.
The original PC-1 (Project Concept-1) of the project was
prepared for PKR 380 million. But through amendments, false delays, and fresh
claims, it went up to PKR 680 million. Yet, nothing was done on ground, and the
track was never laid out. During all this time, the project remained in files,
jumping between concerned departments and the C&W Department. Astoundingly,
a third PC-1 is in the making, with the cost of the project set to increase
three to fourfold at least, and possibly exceed PKR 2 billion.
Sources indicate the initial intention to lay a
"sandwich system" track. Officials are now, however, signifying a
change to the "Piyo System"—allegedly a more up-to-date and costly
design. Curiously, "Piyo" is the word for "father" in the
Hindko language, so cynical observations in local circles are being made that
the "father of all tartan tracks" is being introduced.
The five-year delay in the project has not only blown up the
budget to many folds, but the players are also compelled to leave Peshawar and
move to cities such as Kohat to get their trials and training. In a city which
is supposed to be a sports hub, even the basic facilities cannot be provided to
the athletes. While relevant officials are engaged in preparing "new
project" files in their air-conditioned offices, no contractor has been
blacklisted and no official suspended.
Questions Calling for Answers
Will someone be held accountable for this five-year lag?
Is personal interest behind this public-funded initiative?
Is the Sports Directorate reduced to just being an
institution for producing "PC-1s"?
Is raising a project's budget by renaming it the only option
for each failing project?
These are the questions lingering in the minds of young
athletes, coaches, and sportsmen in Peshawar, but government corridors have
remained deafeningly quiet.
While nothing is going on at the sports ground, the
"genealogy of projects" is definitely being laid out in government
offices. When sportsmen are denied running, and bureaucrats are running after
files, it's obvious that the sports development direction has entirely taken a
U-turn.